Project name: Al Hamza Al Sharqi
Governorate: Diwaniyah
The Executing Company: Al Bued Al Raabie and Difaf Al Nahrayn Contracting Company
Contract cost for the project (in millions): 54,702
Contract cost for the project after appeal: Adopting the prices of the non-executed paragraphs in the quantities table under the original contract
Total spare parts orders in million: 2,877
Contract duration (day): 912
Total additional periods: 0
Total stops/day: 1446
Date of commencement under the contract: 16/6/2019
Date of resumption of work: 16/6/2019
New period after resumption/day: 611 + stops
The new completion date in light of the appeal: 16/2/2021
Financial achievement percentage: 41.00%
Planned completion rate: 43.75%
Technical achievement percentage
Actual before appeal: 36.30%
Previous Actual: 37.3%
Current Actual: 40.5%
Deviation: 3.25%
Observations of problems, obstacles and the current project situation: The project was started on 16/6/2019 according to our letter 7371 on 3/6/2019.. The contract extension was signed with the company executing the project according to our letter 11207 on 9/9/2019. The work progress program submitted by the executing company was approved. The executing company was urged to intensify efforts by working with our letter 11366 on 11/11/2021.
No comment yet, add your voice below!