Azizia Project in Wasit governorate

Project name: Azizia

Governorate: Wasit

The Executing Company: Al-Mansour General Contracting Company

Contract cost for the project (in millions): 69.196

Contract cost for the project after appeal: Adopting the prices of the unimplemented paragraphs in the bill of quantities under the original contract

Total spare orders in million: (-) 285,0

Contract duration (day): 911

Total additional periods: 0

Total stops/day: 1448

Date of commencement under the contract: 16/6/2019

Date of resuming work: 16/6/2019

New period after resumption/day: 463 + stops

The date of the new completion in the light of the appeal: 21/9/2020

Financial achievement percentage: 48.00%

Planned completion rate: 100.00%

Technical achievement percentage:

Actual before appeal: 52.50%

Previous Actual: 57.94%

Current Actual: 60.3%

Deviation: 40.00%

Observations of the problems and obstacles and the position of the current project:

The project was started on 16/6/2019 according to our letter 7369 on 6/3/2019. The contract annex was signed with the company executing the project according to our letter 10477 on 25/8/2019. The work progress program submitted by the executing company has been approved.

The executing company was urged to intensify efforts to work in our letter 1805 on 15/2/2021. It was agreed with the executing company to raise the pace of work on the project.

The executing company was warned under our letter 11870 on 23/11/2021 for the company’s reluctance to implement its contractual obligations.