Project name: dawr alaskan
Governorate: Diwaniyah
The Executing Company: Al-Mansour Company and the Turkish Serhat Company
Contract cost for the project (in millions): 29.59
Contract cost for the project after appeal: Adopting the prices of the non-executed paragraphs in the quantities table under the original contract
Total spare parts orders in million: 2,722
Contract duration (day): 911
Total additional periods: 0
Total stops/day: 1470
Date of commencement under the contract: 16/6/2019
Date of resuming work: 15/9/2019
New period after resumption/day: 585 + stops
The new completion date in light of the appeal: 21/1/2021
Financial achievement percentage: 37.00%
Planned completion rate: 63.00%
Technical achievement percentage
Actual before appeal: 39.00%
Previous Actual : 39.50%
Actual current: 44.6%
Deviation: 19.00%
Observations of problems and obstacles and the position of the current project:
The project was started on 15/9/2019 and as stated in the letter of the resident engineer department for the project No. 71 on 22/9/2019.. The contract annex was signed with the company executing the project according to our letter 10380 on 22/8/2019. Currently, the work is going very slowly due to the lack of financial allocations. A warning letter was sent to the executing company in our letter 2516 on 3/16/2021 with the need to raise the pace of work and overcome the deviation rate. The general manager’s approval was obtained to grant Al-Mansour companies and its partner Sarhat company a one-month grace period starting from 10/1/2021 to intensify efforts and raise the pace of work and the percentage of completion.
Al Hamza Al Sharqi Project
Project name: Al Hamza Al Sharqi
Governorate: Diwaniyah
The Executing Company: Al Bued Al Raabie and Difaf Al Nahrayn Contracting Company
Contract cost for the project (in millions): 54,702
Contract cost for the project after appeal: Adopting the prices of the non-executed paragraphs in the quantities table under the original contract
Total spare parts orders in million: 2,877
Contract duration (day): 912
Total additional periods: 0
Total stops/day: 1446
Date of commencement under the contract: 16/6/2019
Date of resumption of work: 16/6/2019
New period after resumption/day: 611 + stops
The new completion date in light of the appeal: 16/2/2021
Financial achievement percentage: 41.00%
Planned completion rate: 43.75%
Technical achievement percentage
Actual before appeal: 36.30%
Previous Actual: 37.3%
Current Actual: 40.5%
Deviation: 3.25%
Observations of problems, obstacles and the current project situation: The project was started on 16/6/2019 according to our letter 7371 on 3/6/2019.. The contract extension was signed with the company executing the project according to our letter 11207 on 9/9/2019. The work progress program submitted by the executing company was approved. The executing company was urged to intensify efforts by working with our letter 11366 on 11/11/2021.
Residential complex in Kirkuk Sayada
Project name: Residential complex in Kirkuk Sayada
Governorate: Kirkuk
Number of residential units of type (house/apartment): 504 apartments
The name of the executing company: Al-Faw General Company
The nationality of the executing company: Iraqi
Year of assignment: 2007
Contract number / date: None 24/5/2007
Contract amount/ dinars: 47.5
Execution period (day / month): 914
Contractual commencement date: 27/5/2007
Additional periods granted (day): 579
Completion date with extensions: 28/6/2011
The residential complex in Najaf / Hay Al-Salam
Project name: The residential complex in Najaf / Hay Al-Salam
Governorate: Najaf
The number of residential units of their type (house / apartment): 558 apartments
The name of the executing company: Al-Faw General Company
The nationality of the executing company: Iraqi
Year of assignment: 2007
Contract number / date: None 24/5/2007
Contract amount/ dinars: 46.815
Execution period (day / month): 914
Contractual commencement date: 4/8/2007
Additional periods granted (day): 802
Completion date with extensions: 15/4/2012
The residential complex in Maysan / Al-Muddathir and Tabu 2
Project name: The residential complex in Maysan / Al-Muddathir and Tabu 2
Governorate: Maysan
Number of residential units of type (house/apartment): 504 apartments
The name of the executing company: Ard Al Sadu Contracting Company
The nationality of the executing company: Iraqi
Year of assignment: 2007
Contract number / date: 62/ 2/9/2007
Contract amount/ dinars: 39.729
Execution period (day/month): 670
Contractual commencement date: 10/10/2007
Additional periods granted (day): 1326
Completion date with extensions: 28/3/2013
Al-Sidiya residential complex
Project name: Al-Sidiya residential complex
Governorate: Baghdad
Number of residential units of type (house/apartment): 49 houses
The name of the executing company: Al-Farouq State Company
The nationality of the executing company: Iraqi
Year of assignment: 2007
Contract number/date: None 20/5/2007
Contract amount/ dinars: 5.58
Execution period (day / month): 367
Contractual commencement date: 15/8/2007
Additional periods granted (day): 913
Completion date with extensions: 15/2/2011
The housing complex in Baghdad /hay Al-Jihad
Project name: The housing complex in Baghdad /hay Al-Jihad
Governorate: Baghdad
The number of residential units of their type (house / apartment): 167 houses
The name of the executing company: Al-Faw General Company
The nationality of the executing company: Iraqi
Year of assignment: 2007
Contract number / date: None 27/5/2007
Contract amount/ dinars: 19740
Execution period (day / month): 610
Contractual commencement date: 24/7/2007
Additional periods granted (day): 760
Completion date with extensions: 24/4/2011
The residential complex in Nineveh / Al-Hadba
Project name: The residential complex in Nineveh / Al-Hadba
Governorate: Mosul
Number of residential units of type (house/apartment): 504 apartments
The name of the executing company: Al-Mansour State Company
The nationality of the executing company: Iraqi
Year of assignment: 2004
Contract number / date: None 8/3/2004
Contract amount/ dinars: 42,775
Execution period (day / month): 1334
Contractual commencement date: 27/6/2004
Additional periods granted (day): 1898
Completion date with extensions: 3/5/2013
Residential complex in Kirkuk/Bingeh Ali
Project name: Residential complex in Kirkuk/Bingeh Ali
Governorate: Kirkuk
The number of residential units of type (house/apartment): 600 apartments
The name of the executing company: Al-Mansour State Company
The nationality of the executing company: Iraqi
Year of assignment: 2003
Contract number / date: 4/ 15/9/2003
Contract amount/ dinars: 50000
Execution period (day/month): 1080
Contractual commencement date: 1/12/2003
Additional periods granted (day): 419
Completion date with extensions: 19/2/2007
Residential complex in Karbala/ Al-Haidariya
Project name: Residential complex in Karbala/ Al-Haidariya
Governorate: Karbala
Number of residential units of type (house/apartment): 432 apartments
The name of the executing company: Al-Farouq State Company
The nationality of the executing company: Iraqi
Year of assignment: 2003
Contract number / date: 5/ 9/6/2003
Contract amount/ dinars: 30000
Execution period (day / month): 900
Contractual commencement date: 1/12/2003
Additional periods granted (day): 1255
Completion date with extensions: 6/12/2008