Project name: Al-Zubair
Governorate: Basra
The Executing Company: Al-Bilad and Al-Jazeera Contracting Company
Contract cost for the project (in millions): 119,416
Contract cost for the project after appeal:
Total spare parts orders in million: 2.357
Contract duration (day): 913
Total additional periods: 463
Total stops/day: stopped
Date of commencement under the contract: 24/7/2012
Work resume date:
New period after resumption/day: – + stops
The new completion date in light of the appeal: –
Financial achievement percentage: 68.99%
Planned completion rate: 97.00%
Technical achievement percentage: 65.70
Actual before appeal: 65.70%
Previous Actual: 65.70%
Actual current: 65.7%
Deviation: 31.30%
Observations of the problems and obstacles and the position of the current project: The contract was terminated by a court ruling and the Directorate’s intention is to re-announce the project and include it within the investment plan for the coming years, as indicated in our letter 3281 on 8/4/2021
No comment yet, add your voice below!