Shatt Al Arab 1 Project in Al-Basra governorate

Project name: Shatt Al Arab 1

Governorate: Basra

The Executing Company: Al-Rasheed Company

Contract cost for the project (in millions): 58,405

Contract cost for the project after appeal: Adopting the prices of the unimplemented paragraphs in the bill of quantities under the original contract

Total spare parts orders in million: 3.286

Contract duration (day): 913

Total additional periods: 0

Total stops/day: 1500

Date of commencement under the contract: 16/7/2019

Date of resuming work: 27/8/2019

New period after resumption/day: 450 + stops

The date of the new completion in the light of the appeal: 8/10/2020

Financial achievement percentage: 56.00%

Planned completion rate: 83.00%

Technical achievement percentage:

Actual before appeal: 60.00%

Previous Actual: 63.70%

Actual Current: 68.6%

Deviation: 14.42%

Observations of the problems and obstacles and the position of the current project: The project was started on 27/8/2019, as stated in the letter of Resident Engineer Directorate for the project No. 18 on 27/8/201. An annex to the contract was signed with the company executing the project according to our letter 10383 on 22/8/2019. It was agreed to secure the financial allocations by our Directorate and the company indicated its willingness to intensify the efforts and raise the pace of work in the project. The executing company was urged to increase the pace of work in our letter 11261 on 9/1 / 2021, and the executing company was warned under our letter 11869 on 23/11/2021 for the company’s reluctance to implement its contractual obligations.

No comment yet, add your voice below!