Project name: Shatt Al Arab 1
Governorate: Basra
The Executing Company: Al-Rasheed Company
Contract cost for the project (in millions): 58,405
Contract cost for the project after appeal: Adopting the prices of the unimplemented paragraphs in the bill of quantities under the original contract
Total spare parts orders in million: 3.286
Contract duration (day): 913
Total additional periods: 0
Total stops/day: 1500
Date of commencement under the contract: 16/7/2019
Date of resuming work: 27/8/2019
New period after resumption/day: 450 + stops
The date of the new completion in the light of the appeal: 8/10/2020
Financial achievement percentage: 56.00%
Planned completion rate: 83.00%
Technical achievement percentage:
Actual before appeal: 60.00%
Previous Actual: 63.70%
Actual Current: 68.6%
Deviation: 14.42%
Observations of the problems and obstacles and the position of the current project: The project was started on 27/8/2019, as stated in the letter of Resident Engineer Directorate for the project No. 18 on 27/8/201. An annex to the contract was signed with the company executing the project according to our letter 10383 on 22/8/2019. It was agreed to secure the financial allocations by our Directorate and the company indicated its willingness to intensify the efforts and raise the pace of work in the project. The executing company was urged to increase the pace of work in our letter 11261 on 9/1 / 2021, and the executing company was warned under our letter 11869 on 23/11/2021 for the company’s reluctance to implement its contractual obligations.