Shatt Al Arab 1 Project in Al-Basra governorate

Project name: Shatt Al Arab 1

Governorate: Basra

The Executing Company: Al-Rasheed Company

Contract cost for the project (in millions): 58,405

Contract cost for the project after appeal: Adopting the prices of the unimplemented paragraphs in the bill of quantities under the original contract

Total spare parts orders in million: 3.286

Contract duration (day): 913

Total additional periods: 0

Total stops/day: 1500

Date of commencement under the contract: 16/7/2019

Date of resuming work: 27/8/2019

New period after resumption/day: 450 + stops

The date of the new completion in the light of the appeal: 8/10/2020

Financial achievement percentage: 56.00%

Planned completion rate: 83.00%

Technical achievement percentage:

Actual before appeal: 60.00%

Previous Actual: 63.70%

Actual Current: 68.6%

Deviation: 14.42%

Observations of the problems and obstacles and the position of the current project: The project was started on 27/8/2019, as stated in the letter of Resident Engineer Directorate for the project No. 18 on 27/8/201. An annex to the contract was signed with the company executing the project according to our letter 10383 on 22/8/2019. It was agreed to secure the financial allocations by our Directorate and the company indicated its willingness to intensify the efforts and raise the pace of work in the project. The executing company was urged to increase the pace of work in our letter 11261 on 9/1 / 2021, and the executing company was warned under our letter 11869 on 23/11/2021 for the company’s reluctance to implement its contractual obligations.

Al-Zubair project in Al-Basra governorate

Project name: Al-Zubair

Governorate: Basra

The Executing Company: Al-Bilad and Al-Jazeera Contracting Company

Contract cost for the project (in millions): 119,416

Contract cost for the project after appeal:

Total spare parts orders in million: 2.357

Contract duration (day): 913

Total additional periods: 463

Total stops/day: stopped

Date of commencement under the contract: 24/7/2012

Work resume date:

New period after resumption/day: – + stops

The new completion date in light of the appeal: –

Financial achievement percentage: 68.99%

Planned completion rate: 97.00%

Technical achievement percentage: 65.70

Actual before appeal: 65.70%

Previous Actual: 65.70%

Actual current: 65.7%

Deviation: 31.30%

Observations of the problems and obstacles and the position of the current project: The contract was terminated by a court ruling and the Directorate’s intention is to re-announce the project and include it within the investment plan for the coming years, as indicated in our letter 3281 on 8/4/2021

Dawr Alaskan Project

Project name: dawr alaskan
Governorate: Diwaniyah
The Executing Company: Al-Mansour Company and the Turkish Serhat Company
Contract cost for the project (in millions): 29.59
Contract cost for the project after appeal: Adopting the prices of the non-executed paragraphs in the quantities table under the original contract
Total spare parts orders in million: 2,722
Contract duration (day): 911
Total additional periods: 0
Total stops/day: 1470
Date of commencement under the contract: 16/6/2019
Date of resuming work: 15/9/2019
New period after resumption/day: 585 + stops
The new completion date in light of the appeal: 21/1/2021
Financial achievement percentage: 37.00%
Planned completion rate: 63.00%
Technical achievement percentage
Actual before appeal: 39.00%
Previous Actual : 39.50%
Actual current: 44.6%
Deviation: 19.00%
Observations of problems and obstacles and the position of the current project:
The project was started on 15/9/2019 and as stated in the letter of the resident engineer department for the project No. 71 on 22/9/2019.. The contract annex was signed with the company executing the project according to our letter 10380 on 22/8/2019. Currently, the work is going very slowly due to the lack of financial allocations. A warning letter was sent to the executing company in our letter 2516 on 3/16/2021 with the need to raise the pace of work and overcome the deviation rate. The general manager’s approval was obtained to grant Al-Mansour companies and its partner Sarhat company a one-month grace period starting from 10/1/2021 to intensify efforts and raise the pace of work and the percentage of completion.

Al Hamza Al Sharqi Project

Project name: Al Hamza Al Sharqi

Governorate: Diwaniyah

The Executing Company: Al Bued Al Raabie and Difaf Al Nahrayn Contracting Company

Contract cost for the project (in millions): 54,702

Contract cost for the project after appeal: Adopting the prices of the non-executed paragraphs in the quantities table under the original contract

Total spare parts orders in million: 2,877

Contract duration (day): 912

Total additional periods: 0

Total stops/day: 1446

Date of commencement under the contract: 16/6/2019

Date of resumption of work: 16/6/2019

New period after resumption/day: 611 + stops

The new completion date in light of the appeal: 16/2/2021

Financial achievement percentage: 41.00%

Planned completion rate: 43.75%

Technical achievement percentage

Actual before appeal: 36.30%

Previous Actual: 37.3%

Current Actual: 40.5%

Deviation: 3.25%

Observations of problems, obstacles and the current project situation: The project was started on 16/6/2019 according to our letter 7371 on 3/6/2019.. The contract extension was signed with the company executing the project according to our letter 11207 on 9/9/2019. The work progress program submitted by the executing company was approved. The executing company was urged to intensify efforts by working with our letter 11366 on 11/11/2021.

Residential complex in Kirkuk Sayada

Project name: Residential complex in Kirkuk Sayada
Governorate: Kirkuk
Number of residential units of type (house/apartment): 504 apartments
The name of the executing company: Al-Faw General Company
The nationality of the executing company: Iraqi
Year of assignment: 2007
Contract number / date: None 24/5/2007
Contract amount/ dinars: 47.5
Execution period (day / month): 914
Contractual commencement date: 27/5/2007
Additional periods granted (day): 579
Completion date with extensions: 28/6/2011

The residential complex in Najaf / Hay Al-Salam

Project name: The residential complex in Najaf / Hay Al-Salam

Governorate: Najaf

The number of residential units of their type (house / apartment): 558 apartments

The name of the executing company: Al-Faw General Company

The nationality of the executing company: Iraqi

Year of assignment: 2007

Contract number / date: None 24/5/2007

Contract amount/ dinars: 46.815

Execution period (day / month): 914

Contractual commencement date: 4/8/2007

Additional periods granted (day): 802

Completion date with extensions: 15/4/2012

The residential complex in Maysan / Al-Muddathir and Tabu 2

Project name: The residential complex in Maysan / Al-Muddathir and Tabu 2

Governorate: Maysan

Number of residential units of type (house/apartment): 504 apartments

The name of the executing company: Ard Al Sadu Contracting Company

The nationality of the executing company: Iraqi

Year of assignment: 2007

Contract number / date: 62/  2/9/2007

Contract amount/ dinars: 39.729

Execution period (day/month): 670

Contractual commencement date: 10/10/2007

Additional periods granted (day): 1326

Completion date with extensions: 28/3/2013

Al-Sidiya residential complex

Project name: Al-Sidiya residential complex

Governorate: Baghdad

Number of residential units of type (house/apartment): 49 houses

The name of the executing company: Al-Farouq State Company

The nationality of the executing company: Iraqi

Year of assignment: 2007

Contract number/date: None 20/5/2007

Contract amount/ dinars: 5.58

Execution period (day / month): 367

Contractual commencement date: 15/8/2007

Additional periods granted (day): 913

Completion date with extensions: 15/2/2011

The housing complex in Baghdad /hay Al-Jihad

Project name: The housing complex in Baghdad /hay Al-Jihad
Governorate: Baghdad
The number of residential units of their type (house / apartment): 167 houses
The name of the executing company: Al-Faw General Company
The nationality of the executing company: Iraqi
Year of assignment: 2007
Contract number / date: None 27/5/2007
Contract amount/ dinars: 19740
Execution period (day / month): 610
Contractual commencement date: 24/7/2007
Additional periods granted (day): 760
Completion date with extensions: 24/4/2011

The residential complex in Nineveh / Al-Hadba

Project name: The residential complex in Nineveh / Al-Hadba
Governorate: Mosul
Number of residential units of type (house/apartment): 504 apartments
The name of the executing company: Al-Mansour State Company
The nationality of the executing company: Iraqi
Year of assignment: 2004
Contract number / date: None 8/3/2004
Contract amount/ dinars: 42,775
Execution period (day / month): 1334
Contractual commencement date: 27/6/2004
Additional periods granted (day): 1898
Completion date with extensions: 3/5/2013