Azizia Project in Wasit governorate

Project name: Azizia

Governorate: Wasit

The Executing Company: Al-Mansour General Contracting Company

Contract cost for the project (in millions): 69.196

Contract cost for the project after appeal: Adopting the prices of the unimplemented paragraphs in the bill of quantities under the original contract

Total spare orders in million: (-) 285,0

Contract duration (day): 911

Total additional periods: 0

Total stops/day: 1448

Date of commencement under the contract: 16/6/2019

Date of resuming work: 16/6/2019

New period after resumption/day: 463 + stops

The date of the new completion in the light of the appeal: 21/9/2020

Financial achievement percentage: 48.00%

Planned completion rate: 100.00%

Technical achievement percentage:

Actual before appeal: 52.50%

Previous Actual: 57.94%

Current Actual: 60.3%

Deviation: 40.00%

Observations of the problems and obstacles and the position of the current project:

The project was started on 16/6/2019 according to our letter 7369 on 6/3/2019. The contract annex was signed with the company executing the project according to our letter 10477 on 25/8/2019. The work progress program submitted by the executing company has been approved.

The executing company was urged to intensify efforts to work in our letter 1805 on 15/2/2021. It was agreed with the executing company to raise the pace of work on the project.

The executing company was warned under our letter 11870 on 23/11/2021 for the company’s reluctance to implement its contractual obligations.

Shatt Al Arab 2 Project

Project name: Shatt Al Arab 2

Governorate: Basra

Executing Company: Stratos Corporation

Contract cost for the project (in millions): 159,256

Contract cost for the project after appeal: Adopting the prices of the unimplemented paragraphs in the bill of quantities under the original contract

Total spare parts orders in million: 232,0

Contract duration (day): 820

Total additional periods: 0

Total stops/day: 1598

Date of commencement under the contract: 26/12/2012

Date of resuming work: 29/8/2019

New period after resumption/day: 590 + stops

The date of the new completion in the light of the appeal: 26/1/2021

Financial achievement percentage: 18.89%

Planned completion rate: 56.12%

Technical achievement percentage:

Actual before appeal: 33.24%

Previous Actual: 33.24%

Actual current: 33.4%

Deviation: 22.72%

Observations of problems and obstacles and the position of the current project: The project was started on August 29, 2019 as stated in the letter of the resident engineer directorate No. 11 on August 29, 2019. The contract extension was signed with the company executing the project according to our letter 10382 on 22/8/2019.

The project was stopped in October 2019 due to the demonstrations, which led to the withdrawal of the executing company to Iran due to the security situation. A meeting was held with the company executing the project recently for the purpose of starting work and it is now in the process of preparing the site.

 

Work was resumed on the site on 27/4/2021, as the executing company was urged to increase the pace of work according to our letter 6849 on 7/8/2021.

Shatt Al Arab 1 Project in Al-Basra governorate

Project name: Shatt Al Arab 1

Governorate: Basra

The Executing Company: Al-Rasheed Company

Contract cost for the project (in millions): 58,405

Contract cost for the project after appeal: Adopting the prices of the unimplemented paragraphs in the bill of quantities under the original contract

Total spare parts orders in million: 3.286

Contract duration (day): 913

Total additional periods: 0

Total stops/day: 1500

Date of commencement under the contract: 16/7/2019

Date of resuming work: 27/8/2019

New period after resumption/day: 450 + stops

The date of the new completion in the light of the appeal: 8/10/2020

Financial achievement percentage: 56.00%

Planned completion rate: 83.00%

Technical achievement percentage:

Actual before appeal: 60.00%

Previous Actual: 63.70%

Actual Current: 68.6%

Deviation: 14.42%

Observations of the problems and obstacles and the position of the current project: The project was started on 27/8/2019, as stated in the letter of Resident Engineer Directorate for the project No. 18 on 27/8/201. An annex to the contract was signed with the company executing the project according to our letter 10383 on 22/8/2019. It was agreed to secure the financial allocations by our Directorate and the company indicated its willingness to intensify the efforts and raise the pace of work in the project. The executing company was urged to increase the pace of work in our letter 11261 on 9/1 / 2021, and the executing company was warned under our letter 11869 on 23/11/2021 for the company’s reluctance to implement its contractual obligations.

Al-Zubair project in Al-Basra governorate

Project name: Al-Zubair

Governorate: Basra

The Executing Company: Al-Bilad and Al-Jazeera Contracting Company

Contract cost for the project (in millions): 119,416

Contract cost for the project after appeal:

Total spare parts orders in million: 2.357

Contract duration (day): 913

Total additional periods: 463

Total stops/day: stopped

Date of commencement under the contract: 24/7/2012

Work resume date:

New period after resumption/day: – + stops

The new completion date in light of the appeal: –

Financial achievement percentage: 68.99%

Planned completion rate: 97.00%

Technical achievement percentage: 65.70

Actual before appeal: 65.70%

Previous Actual: 65.70%

Actual current: 65.7%

Deviation: 31.30%

Observations of the problems and obstacles and the position of the current project: The contract was terminated by a court ruling and the Directorate’s intention is to re-announce the project and include it within the investment plan for the coming years, as indicated in our letter 3281 on 8/4/2021

Dawr Alaskan Project

Project name: dawr alaskan
Governorate: Diwaniyah
The Executing Company: Al-Mansour Company and the Turkish Serhat Company
Contract cost for the project (in millions): 29.59
Contract cost for the project after appeal: Adopting the prices of the non-executed paragraphs in the quantities table under the original contract
Total spare parts orders in million: 2,722
Contract duration (day): 911
Total additional periods: 0
Total stops/day: 1470
Date of commencement under the contract: 16/6/2019
Date of resuming work: 15/9/2019
New period after resumption/day: 585 + stops
The new completion date in light of the appeal: 21/1/2021
Financial achievement percentage: 37.00%
Planned completion rate: 63.00%
Technical achievement percentage
Actual before appeal: 39.00%
Previous Actual : 39.50%
Actual current: 44.6%
Deviation: 19.00%
Observations of problems and obstacles and the position of the current project:
The project was started on 15/9/2019 and as stated in the letter of the resident engineer department for the project No. 71 on 22/9/2019.. The contract annex was signed with the company executing the project according to our letter 10380 on 22/8/2019. Currently, the work is going very slowly due to the lack of financial allocations. A warning letter was sent to the executing company in our letter 2516 on 3/16/2021 with the need to raise the pace of work and overcome the deviation rate. The general manager’s approval was obtained to grant Al-Mansour companies and its partner Sarhat company a one-month grace period starting from 10/1/2021 to intensify efforts and raise the pace of work and the percentage of completion.

Al Hamza Al Sharqi Project

Project name: Al Hamza Al Sharqi

Governorate: Diwaniyah

The Executing Company: Al Bued Al Raabie and Difaf Al Nahrayn Contracting Company

Contract cost for the project (in millions): 54,702

Contract cost for the project after appeal: Adopting the prices of the non-executed paragraphs in the quantities table under the original contract

Total spare parts orders in million: 2,877

Contract duration (day): 912

Total additional periods: 0

Total stops/day: 1446

Date of commencement under the contract: 16/6/2019

Date of resumption of work: 16/6/2019

New period after resumption/day: 611 + stops

The new completion date in light of the appeal: 16/2/2021

Financial achievement percentage: 41.00%

Planned completion rate: 43.75%

Technical achievement percentage

Actual before appeal: 36.30%

Previous Actual: 37.3%

Current Actual: 40.5%

Deviation: 3.25%

Observations of problems, obstacles and the current project situation: The project was started on 16/6/2019 according to our letter 7371 on 3/6/2019.. The contract extension was signed with the company executing the project according to our letter 11207 on 9/9/2019. The work progress program submitted by the executing company was approved. The executing company was urged to intensify efforts by working with our letter 11366 on 11/11/2021.