Project name: Azizia
Governorate: Wasit
The Executing Company: Al-Mansour General Contracting Company
Contract cost for the project (in millions): 69.196
Contract cost for the project after appeal: Adopting the prices of the unimplemented paragraphs in the bill of quantities under the original contract
Total spare orders in million: (-) 285,0
Contract duration (day): 911
Total additional periods: 0
Total stops/day: 1448
Date of commencement under the contract: 16/6/2019
Date of resuming work: 16/6/2019
New period after resumption/day: 463 + stops
The date of the new completion in the light of the appeal: 21/9/2020
Financial achievement percentage: 48.00%
Planned completion rate: 100.00%
Technical achievement percentage:
Actual before appeal: 52.50%
Previous Actual: 57.94%
Current Actual: 60.3%
Deviation: 40.00%
Observations of the problems and obstacles and the position of the current project:
The project was started on 16/6/2019 according to our letter 7369 on 6/3/2019. The contract annex was signed with the company executing the project according to our letter 10477 on 25/8/2019. The work progress program submitted by the executing company has been approved.
The executing company was urged to intensify efforts to work in our letter 1805 on 15/2/2021. It was agreed with the executing company to raise the pace of work on the project.
The executing company was warned under our letter 11870 on 23/11/2021 for the company’s reluctance to implement its contractual obligations.